You Tube Video regarding closure: http://youtu.be/DsBcESgt1yk?a
Detour Map: http://www.dot.ca.gov/dist10/pages/pressreleases/Detour%208_2010_rev%20small-aug27.pdf
Wednesday, August 18, 2010
Friday, July 23, 2010
EASTBOUND STATE ROUTE 152 FROM SAN LUIS DRIVE TO VOLTA ROAD IN MERCED COUNTY
Merced County - The California Department of Transportation (Caltrans) will close the #1 (left) and #2 (right) lanes, alternately, on eastbound State Route 152 from San Luis Drive to Volta Road.
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 4:00 a.m. until 2:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $945,000 project is Tom Mayo Construction Inc. of Stockton, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 4:00 a.m. until 2:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $945,000 project is Tom Mayo Construction Inc. of Stockton, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
STATE ROUTE 132 AT STATE ROUTE 33 IN SAN JOAQUIN COUNTY
San Joaquin County - The California Department of Transportation (Caltrans) will perform one-way traffic control on State Route 132 (SR-132) at the SR-132/SR-33 overhead.
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $201,600 project is Victory Engineers Inc. of Fresno, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $201,600 project is Victory Engineers Inc. of Fresno, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Labels:
Caltrans,
commuter,
highway,
Road work,
roadwork,
san joaquin,
slow for the cone zone
STATE ROUTE 124 FROM STATE ROUTE 88 TO WASHINGTON STREET IN AMADOR COUNTY
Amador County - The California Department of Transportation (Caltrans) will perform one-way traffic control on State Route 124 (SR-124) from the SR-88/SR-124 junction to Washington Street.
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $1.8 million project is George Reed Inc. of Modesto, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $1.8 million project is George Reed Inc. of Modesto, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
SOUTHBOUND STATE ROUTE 99 AT GOLDEN STATE BOULEVARD IN MERCED COUNTY
Merced County - The California Department of Transportation (Caltrans) will close the southbound Golden State Boulevard on-ramp on State Route 99.
Work will occur on Thursday, July 29, 2010, from 8:30 a.m. until 2:00 p.m.
Crews will cut and prune the trees in this location.
Motorists should expect 5 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Work will occur on Thursday, July 29, 2010, from 8:30 a.m. until 2:00 p.m.
Crews will cut and prune the trees in this location.
Motorists should expect 5 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
STATE ROUTE 88 FROM STATE ROUTE 124 TO STATE ROUTE 104 IN AMADOR COUNTY
Amador County - The California Department of Transportation (Caltrans) will perform one-way traffic control on State Route 88 (SR-88) from the SR-88/SR-124 junction in Ione to the SR-88/SR-104 junction in Martell.
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $1.8 million project is George Reed Inc. of Modesto, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Work will begin on Monday, July 26, 2010, through Friday, July 30, 2010, from 6:00 a.m. until 6:00 p.m.
Crews will pave the roadway in this location.
Motorists should expect 15 minute delays. Alternate routes should be taken whenever possible.
This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for the $1.8 million project is George Reed Inc. of Modesto, CA.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
http://www.dot.ca.gov/
###
Friday, July 9, 2010
FULL HIGHWAY CLOSURE - STATE ROUTE 99 WHITMORE INTERCHANGE PROJECT IN STANISLAUS COUNTY
Stanislaus County - The California Department of Transportation (Caltrans) will close northbound State Route 99 (SR-99) from the Pine Street overcrossing to Hatch Road in Ceres.
Work will begin on Monday, July 12, 2010, through Thursday, July 16, 2010, from 11:00 p.m. until 4:00 a.m.
Crews will work on the falsework for the new interchange.
SR-99 northbound detour is:
• northbound off-ramp to 4th Street;
• Continue north on El Camino Avenue;
• Cross Whitmore Avenue to the new on-ramp to northbound SR-99.
This full highway closure is necessary to ensure the safety of motorists and workers in the area.
Motorists should expect 10 minute delays. Alternate routes should be taken whenever possible. This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for this $26 million project is Nehemiah Construction of Benicia, CA. The SR-99 Whitmore Avenue Interchange Project will alleviate peak hour congestion along Whitmore Avenue with a new wider overcrossing/overhead and widen Whitmore Avenue to four lanes from Blaker Road and Central Avenue.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
www.dot.ca.gov
###
Work will begin on Monday, July 12, 2010, through Thursday, July 16, 2010, from 11:00 p.m. until 4:00 a.m.
Crews will work on the falsework for the new interchange.
SR-99 northbound detour is:
• northbound off-ramp to 4th Street;
• Continue north on El Camino Avenue;
• Cross Whitmore Avenue to the new on-ramp to northbound SR-99.
This full highway closure is necessary to ensure the safety of motorists and workers in the area.
Motorists should expect 10 minute delays. Alternate routes should be taken whenever possible. This work is scheduled to begin as listed, but is subject to change based on weather conditions.
The contractor for this $26 million project is Nehemiah Construction of Benicia, CA. The SR-99 Whitmore Avenue Interchange Project will alleviate peak hour congestion along Whitmore Avenue with a new wider overcrossing/overhead and widen Whitmore Avenue to four lanes from Blaker Road and Central Avenue.
#
For the safety of workers and other motorists, please Slow For the Cone Zone.
##
www.dot.ca.gov
###
Subscribe to: